Issue
Across five floors, from the 3rd to the 7th, a large amount of electrical equipment had to be in place in time for the opening: sales floor lighting and outlets, power for display TVs, and wiring for POS, LAN and security cameras.
Action
We were awarded the full electrical package and served as the single point of contact, together with the air conditioning, ventilation, plumbing and fire and life safety work. From April, we installed main lines, lighting and outlet wiring, low-voltage wiring and distribution boards on each floor, and before the opening our own employees also joined the electrical work.
Result
Work started in March 2016, the store opened in November, and we completed the work by December. Since the opening, we have continued to receive orders from the same store for electrical repairs, added circuits and electrical changes when the sales floor is rearranged.